Инжиниринг

Electrical Engineering Department

Electrical Engineering Department can both accomplish individual projects and contribute to integrated engineering tasks. Project planning is exercised generally for new construction as well as for objects under rebuilding and upgrading. The major areas of engineering are as follows:

  • 10(6) kV indoor switchgears, 0.4 kV switchgears, 0.4 kV power control switchboards;
  • 0.4-110 kV overhead transmission lines;
  • 0.4-10 kV cable power lines;
  • 0.4-10 kV supply and distribution networks;
  • indoor and outdoor electric lighting systems;
  • 110/35/10 kV transformer stations;
  • substructure electrochemical protection;
  • lightning-discharge protection and grounding;
  • relaying and automation calculations.

Major projects:

  • "Starolikeevo" line operations dispatcher station. Major repair of 35 kV overhead transmission line;
  • "Jamburgskaya" gas refrigeration station compressor plant. Captive power plant. 10 kV indoor switchgear reconstruction;
  • "SRTO-Torzhok" gas-main pipeline. "Sindorskaya" booster station. 10 kV indoor switchgear reconstruction;
  • "Aleksandrovskaya-Anzhero-Sudzhensk" oil-main pipeline. "Parabel" oil pump station. Power control switchboard # 34 reconstruction;
  • Teleautomation of the "Oil and Gas Refinery Plant-Parabel-Kuzbass" gas transmission pipeline owned by LLC "Gazprom Transgaz Tomsk".
  • Booster compressor station #1. Novosibirsk District Oil Pipeline Agency. "Anzherskaya" line operations dispatcher station. Reconstruction;
  • JSC "Seversky vodokanal". Building #1 and Building #2 lightning-discharge protection and grounding.
  • "Primorsk" commercial seaport. Sea terminal for refined oil-product transshipment. Power supply (powered from existing networks owned by JSC "Transneft"). Reconstruction.
  • 110/6 kV substation. Control current system with battery and rectifier unit changing. Omsk District Oil Pipeline Agency. "Barabinskaya" line operations dispatcher station. Major repair.